When the cooling tower we bought comes, we need to know some installation steps of the cooling tower. What are the specific steps? Below Haike Xiaobian will talk to you together.
1. Install water tower sink and basin floor
The sink is placed on the central foundation, the basin periphery is supported on the bottom frame, and the basin inner circle is fixed on the flange surface of the sink.
2. Install central throat pipe, central throat clamp and girder support frame of cooling tower
The center throat shall be installed vertically on the flume throat curve, and then the center throat clamp shall be installed, and then the girth bracket shall be installed.
3. Install the heat sink bracket and heat sink film
Connect the heat sink bracket to the center throat clip, but make sure it is horizontal and vertical. Verify that all pieces are strung together, tighten all screws, and then put in the composite radiating film.
4. Sealing the joint between the birdbasin and the body
As the water tower is a multi-component type, it is necessary to seal the gap with resin and fiber after installation.
5. Pre-build cement foundation and install water tower support frame
According to the instructions, the foundation of the concrete or steel frame can be prefabricated, and then the bottom basin support frame of the water tower can be assembled into a circular frame shape with the same level.
6. First choose the appropriate installation site
Pay attention to the loading and ventilation conditions of the cooling tower installation position.
7. Install motor and fan
Install the motor horizontally on the top of the casing body, then put the motor and reducer, and then install the fan group.
8. Install enclosure enclosure and ladder
Place the shell body on the body bracket, assemble and tighten the screws around the heat sink, and then install the ladder in the designated position.
9. Install cooling tower nozzle, pipe hoist and spray pipe
The nozzle is installed on the top of the central throat pipe, and then the hanging pipe appliance is set on the top of the nozzle, and then the sprinkler pipe is pushed horizontally into the nozzle, and the steel line of the hanging pipe is used for tension control, until the sprinkler pipe is in a horizontal position, and the sprinkler hole should be installed 10 degrees backward with the vertical line.
Is trlon introduce everyone to air conditioning cooling towers above the assembling process, guangdong trlon energy-saving air conditioning equipment co., LTD. Is committed to closed cooling towers, closed cooling towers, closed cooling tower, dry wet joint closed cooling tower equipment manufacturing and sales, trlon air conditioning has advanced processing equipment, mature production and processing craft, can guarantee the closed cooling tower in guangdong, enclosed price of cooling tower, closed cooling tower, dry wet joint quality of closed cooling tower and the acquisition price, let customer acquisition cost-effective equipment, if you have cooperation intention, please call to negotiate cooperation.
Article Address:https://www.trlen.com/baike/342.html
Guangdong Trlon Energy-saving Air Conditioning Equipment Co., Ltd.
Contact:Mr. Wang
Free Hotline:4008-8383-95
Company Email:sales@trlon.com
Web Site:https://www.trlen.com/
Company Address: 1916A, Block A, David Donglong Business Building, Longhua, Longhua District, Shenzhen